Twin-Screw floating fish feed extruder machine Start-Up Checklist: Pre-Run Inspection Items Before First Operation

2026/10/27

Jüngste unternehmensnachrichten über Twin-Screw floating fish feed extruder machine Start-Up Checklist: Pre-Run Inspection Items Before First Operation
Quick answer

Twin-Screw floating fish feed extruder machine start-up checks run in one order: power and safety devices, feeder direction and hopper, screws and barrel, lubrication points, steam and water, preheat with a 30 to 45 minute hold, die and cutter gap, then a one to two minute empty run before the running-in period.

Before the first start-up there are no previous readings to compare against, so every check is taken from the machine documents. From the second run onward, the previous shift readings show what changed.

Eight checks carry the twin-screw aquatic feed extruder machine from the incoming supply to the first turn of the screws. Each ends with a condition that has to be met before the next begins. The two numbers that decide the outcome are the 30 to 45 minute hold and the cutter gap at every blade.


neueste Unternehmensnachrichten über Twin-Screw floating fish feed extruder machine Start-Up Checklist: Pre-Run Inspection Items Before First Operation  0

neueste Unternehmensnachrichten über Twin-Screw floating fish feed extruder machine Start-Up Checklist: Pre-Run Inspection Items Before First Operation  1

Key takeaways
  • Each barrel section is held at its set value for 30 to 45 minutes, with the set point within ±5 °C. Up to 60 minutes on larger machines.
  • Every cutter blade sits at the same gap from the die core plane. No blade is loaded against the die face to close a gap.
  • Conditioner steam is dry and saturated at 0.2–0.4 MPa. Jacket steam stays at or below 0.4 MPa, with fluctuation within 0.05 MPa.
  • A new Twin screw floating fish food pellet maker machine needs grease at the bearing points before the first run, and the gearbox level is read against the sight mark.
  • The empty run lasts one to two minutes. During the running-in period the main motor stays below its rated value with about 10% margin.

Confirm the Power Supply, Instruments and Safety Devices Before the First Start-Up

The incoming supply is checked against the machine documents before the main breaker is closed.

Read voltage, number of phases and frequency at the plant terminals and compare them with the motor nameplate and the electrical drawing. Confirm the earth conductor is connected at the panel and at the machine frame. Inside the cabinet, look for parts that moved in transit and packing material among the wires.

Power the control circuit only, then read every instrument. Temperature controllers show ambient temperature, while pressure gauges and the ammeter sit at zero. Test each alarm at the sensor: overload, over-temperature and the lubrication low-level alarm. Press the emergency stop once and confirm the main motor contactor drops out until it is reset.

Site voltage and the steam pressure at the plant boundary decide several settings in the documents, and both are often unmeasured when the machine arrives. Send both through the contact page before the first power-up.

Check the Feeder Rotation Direction and Clean the Hopper Before the First Run

The feeder motor is a separate drive and can run in the wrong direction after transport or a reconnection on site.

Jog the feeder for two or three seconds with the hopper empty and watch the shaft against the arrow on the casing. A feeder running backwards pushes material up into the hopper, and the motor sounds normal while it does it. Change two phases at the feeder terminals and jog again.

Clean the hopper, the feeder screw and the discharge throat. Remove packing, tools and the rust-preventive film with a dry cloth, and confirm the throat is open. Set the feed rate control to zero before the drive starts.

Check the Two Screws and the Barrel for Foreign Material and Loose Parts

Open the barrel and look at both screws and the sleeves before anything is powered.

On a Twin screw floating fish food extruder machine, the gap between the two screws is the first place a foreign object lodges, and a screw that has picked up packing or a dropped bolt will not turn. Check the screw couplings and shaft fasteners for tightness. No weight goes on the barrel and nobody stands on it.

Turn the main shaft by hand or with the barring device through one full revolution in each direction, with no tight spot and no contact sound. If the shaft will not turn, find the cause before the motor starts, because a start on a jammed screw loads the gearbox and the couplings in one step. Barrel and screw geometry differs from a single-screw machine, and the comparison of single-screw and twin-screw fish feed extruders sets out where the two differ.

Photographs of the barrel interior and of the screw couplings as received settle most of these questions early. Send them through the contact page with the serial number.

Confirm Every Lubrication Point Has Been Filled Before the First Run

Lubrication is the most common first-run omission because a new machine is assumed to arrive filled.

Read the gearbox level against the sight mark with the Twin screw floating fish food maker machine level on its foundation. A level below the mark is topped up with the oil grade in the documents, and a level above the mark is corrected, because an overfilled gearbox pushes oil past the seals. Milky or discoloured oil points to water in the housing, so the source is found before more oil goes in.

Add grease at each bearing position, at the front gear of the differential conditioner and at the feeder gear motor. Pump until grease shows at the seal or the relief point, then stop, and mark the point off on the commissioning sheet.

Check Steam Pressure, Water Supply and Pipe Leaks Before the First Batch

Steam pressure, steam quality and water flow are confirmed before any material enters the conditioner.

Conditioner steam is dry and saturated at 0.2–0.4 MPa. Jacket steam stays at or below 0.4 MPa, with fluctuation within 0.05 MPa. Open the drain at the low point of the steam line and let it run until the line delivers dry steam. A line started wet carries water into the conditioner, and that water adds moisture the recipe does not account for.

Check the water line at the injection point: flow present, no leak at the joints, check valve holding. Walk the valve list against the commissioning sheet, from the steam header and the conditioner steam valve to the jacket steam valve, the water injection valve and every drain. Read the gauges with the lines pressurised.

Set the Barrel Temperatures and Hold Them for 30 to 45 Minutes

Hold every barrel section at its set value for 30 to 45 minutes before the first material enters, and keep the set point within ±5 °C. Larger machines and materials with a higher melting point take up to 60 minutes. A controller that has reached its set value has heated the sensor, and the wall behind the sensor is still catching up.

Set each section from the section count and the temperature points listed in the documents supplied with the machine. A section without a measuring point cannot be confirmed, so the points are counted before the set values are entered.

The last barrel section runs at 130–140 °C in normal production, depending on the recipe. At the conditioner outlet, material reaches 85 °C or above, holds together when squeezed in the hand and breaks apart when dropped.

Table 1 gives the Twin screw floating fish food maker machinerange, so preheat time and heater capacity can be matched to the output class on site.

Table 1. Wet-type twin-screw fish feed extruder range

Model
Output (kg/h)
Main motor (kW)
Conditioner (kW)
Type 65
250–300
22
3
Type 70
500–600
45
3
Type 85
1200–1500
90
5.5
Type 95
2000–2500
110
11
Type 120
3000–4000
160
15 + 7.5

The section count and the temperature point table are specific to each machine, and both are often missing on site. How the processing temperature of an extruded feed is controlled covers what changes on each section once the run starts.

Check the Die, the Cutter Gap and the Blade Contact

The die, the cutter gap and the blade contact are the last mechanical settings before the first batch.

Clean every die hole and look through each one against a light. Material left in a hole from the supplier's test run blocks that hole on the first batch. Seat the die, fit the gasket and tighten the clamps in the sequence in the documents, with the barrel empty.

Measure the gap between each cutter blade and the die core plane with a feeler gauge, and bring every blade to the same value. A blade forced against the die face to close a gap loads the blade shaft and wears the die face. Turn the cutter shaft by hand through one full revolution and confirm no contact at any point.

Material fineness has to match the die hole. For holes of φ2.0–2.5 mm, 95% of the material passes 80 mesh and 100% passes 60 mesh. For φ3.0–3.5 mm, 95% passes 60 mesh and 100% passes 40 mesh. Above φ3.5 mm, 80% passes 60 mesh and 100% passes 20 mesh.

The operating sequence after the first run covers the feed steps and the checks that follow the first cut pellet.

Run the Twin screw floating fish feed pellet maker machine Empty for One to Two Minutes, Then Start the Running-In Period

With the die and cutter fitted and the feeder at zero, run the main motor for one to two minutes and listen to the drive.

The sound has to stay even, with no knock from the gearbox, no vibration at the barrel and a current reading that holds at a steady low value. A knock, smoke or a step change in current calls for an emergency stop and a check of the cause before the run continues.

After the empty run, start the feeder at a low rate, add water at the injection point and raise the feed rate in steps while current, barrel temperatures and the pellet are watched together. The 1 t/h twin-screw fish feed extruder test follows the same order from the empty run to the first pellet.

The running-in period then follows the period stated by the supplier. During it, the main motor load stays below the rated value with about 10% margin, and the end is judged by the cumulative output figure in the documents.

Conclusion

Every check above is made once in the life of the Twin screw fish feed pellet maker machine, and the order is fixed: supply, feeder, barrel, lubrication, steam and water, preheat, die and cutter, empty run. The 30 to 45 minute hold and the blade-by-blade gap decide most of what happens on the first batch.

Write each confirmed item on the commissioning sheet, and the second run starts from a set of readings instead of from zero.

Send the site voltage, the steam pressure at the boiler outlet, photographs of the barrel interior as received and the serial number through the contact page. The section count and temperature point table are issued against the serial number, and the 70–110 mm screw diameter twin-screw fish feed extruder shows the layout those documents refer to.

Frequently asked questions

Twin-Screw Fish Feed Extruder Start-Up: Common Questions

Which item is most often missed on a new Twin screw fish feed making machine?

Grease at the bearing points and the gearbox level. A new machine is assumed to arrive filled, and the first run then starts on a partly dry bearing. The cutter blade gap is the second item, checked at one blade and not at all of them.

The oil level is already at the sight mark. Does it need topping up?

No. A level at the mark is correct, and oil above the mark is pushed past the seals. Read the level again after the first hours of running, because lines and cavities fill during that time. A level that falls points to a leak at a joint.

Can material be fed into the twin-screw floating fish feed extruder as soon as the barrel zones reach their setpoints?

No. The hold is 30 to 45 minutes at the set value, with the set point within ±5 °C, and up to 60 minutes on a larger machine or with a material of higher melting point. The hold covers the barrel wall behind the sensor, which lags the reading.

What should be done if the steam arrives wet?

Open the drain at the low point of the line and run it until the steam is dry, then check the trap. Conditioner steam is dry and saturated at 0.2–0.4 MPa, jacket steam at or below 0.4 MPa with fluctuation within 0.05 MPa. Water in the steam enters the conditioner as moisture the recipe does not include.

The shaft will not turn when barred over. What is checked first?

Foreign material in the intermeshing zone, a fastener left inside the barrel, and the barring device itself, which has to be released before the motor turns the shaft. Transit damage to a screw or a sleeve is the next item. The motor is not started to free a jammed screw.

How long should the empty run last of the Twin screw fish feed extruder machine?

One to two minutes, with the die and cutter fitted and the feeder at zero. That is long enough to hear the gearbox and feel the barrel, and short enough that no heat builds with an empty screw. An uneven sound, vibration or a current reading that does not hold ends the run.

Can the Twin screw floating fish feed production machine run at full load during the running-in period?

No. The main motor stays below its rated value with about 10% margin, and the load is raised in steps as the outlet condition holds. The end of the running-in period follows the period stated by the supplier, judged by the cumulative output figure in the documents.